Update particulars below.

Maryland construction status

  • Continued use of Offsite Areas as laydown, offsite fabrication, and parking/offices, including maintenance of E&S controls at Offsite Area A (OAA).
  • Installation of heat shields on South Ground Flare runners, wall supports, and aggregate.
  • Installation of ethane/propane pumps in refrigerant storage area.
  • Installation of the 5 remaining ACHE in the main liquefaction pipe rack.
  • Setting of sump pumps in LNG sump.
  • Insulation of the propane suction drums and receiver.
  • Installation of fire and gas detection system, temporary fence, and lighting in Power Block.
  • Installation of instruments in STG area.
  • Installation of firefighting (CO2) and cooling water instrumentation for north and south GTs.
  • Instruments and tubing for GT north and south lube oil system and inlet filter house.
  • Installation of structure over amine sump, truck unloading area and installation of structure at south jetty platform.
  • Support steel for STG duct work.
  • Completion of the fire water system in Power Block.
  • Installation of cooling water piping for the south GT Helper Motor.
  • Commissioning activities have been completed for the following systems: first fire auxiliary boiler; aqualaze cleaning of the ACC collection headers, ducts, and condensate piping; DCS loop checks auxiliary boilers and associated equipment.
  • ACC cooling fan pitching to vendor recommendation with follow-up test runs.
  • Checkout and commissioning of the Emergency Diesel Generator.
  • Installation of steam blow piping and silencers.
  • Nitrogen stripper and stabilizer dress out.
  • Installation of the rails for the cleaning system on the ACC.
  • Installation of the STG Ductwork Sections.
  • Fire proofing of level 3 and 4 in the main liquefaction pipe rack.
  • Fire water system in liquefaction and pre-treatment.
  • North/south and east/west pipe racks- mixed refrigerant, propane, natural gas, flare, and utilities.
  • Pipe testing is ongoing for mixed refrigerant, propane, and natural gas services.
  • North/south rack- Natural gas, flare, and utilities.
  • Pipe testing is ongoing for Natural gas, flare, and utilities.
  • Gas turbine buildings - propane, mixed refrigerant, and utilities.
  • Pipe testing is ongoing for mixed refrigerant, propane, and utility services. Air slows and cleaning of the propane and MR piping in the north gas turbine building.
  • South flare- Nitrogen piping
  • South Jetty- LNG