According to the notice, FERC will issue its final Environmental Impact Statement (EIS) on 12 October 2018, and has established a 90-day Federal Authorisation Decision Deadline on 10 January 2019.

Assuming a favourable decision, Tellurian expects that this schedule will allow it to begin construction of Driftwood LNG in early 2019, pending a final investment decision by Tellurian.