The companies selected in the public procurement procedure are committed to obtain all the necessary arrangements, approvals, opinions, permits and decisions and submit a complete package of engineering design documents to the investor by the 1 Q 2020. Both companies will also provide the author’s supervision during the construction process.

The offshore pipeline will reach Polish coast of the Baltic Sea in the West Pomeranian Province. Depending on the finally selected route of the offshore pipeline, the transmission system will be 230 – 300 km long. Moreover, the project provides for the construction of a new gas compressor station in Gustorzyn, and the expansion of two compressor stations in Odolanów and Goleniów.

The investment projects described above are necessary for the functioning of the Polish transmission system handling increased volumes of natural gas obtained from diversified supply sources, expansion of the LNG Terminal in Swinoujscie and the construction of the offshore gas pipeline between Denmark and Poland.